Sorry, you need to have JavaScript enabled and the latest version of Adobe Flash Player installed to view this content.

Alternatively you can view the accessible alternative.

Capital Projects:

Viaduct Bearing Replacement

Current works on site:

Balfour Beatty commenced work on site on 17 May 2010.

The project is now well under way on both approach viaducts, and is on target to be completed as planned before the end of 2012.

No disruption to daytime traffic is anticipated as a result of this project. It was expected that some overnight restrictions might be necessary to ensure that the jacking and lowering of the bridge deck can be sufficiently controlled, however this has not proved necessary so far.

Background:

A major project to replace the bearings on the Forth Road Bridge’s north and south approach viaducts began in May 2010. The project is scheduled for completion at the end of 2012.

The approach viaducts sit at either end of the bridge on each shore, connecting the A90 with the main body of the suspension bridge. Unlike the middle of the bridge, which is suspended from the main cables, the approach viaducts are supported by reinforced concrete piers. Steel bearings sit on top of these piers, allowing the deck to move as required by changes in temperature and traffic loading.

The project will involve jacking up the deck to allow removal of the existing bearings. The steel box girders that support the concrete deck will be strengthened at the jacking points, and reinforced concrete corbels added to the sides of the piers to accommodate the jacks, an alteration for which listed building consent has been granted. Concrete repairs will be carried out on the piers and a system of cathodic protection installed.

It was always expected that these bearings would need to be replaced after a few decades. Similar replacements have been carried out on viaducts all over the world, most recently in Scotland on the Tay Bridge. Like all moving parts, the bearings will eventually wear out, so it’s important that they are replaced now before they present any safety risk.

Balfour Beatty Civil Engineering have been contracted to carry out the works under the supervision of consulting engineers Atkins, following a competitive tender process involving six potential contractors. Balfour Beatty scored highly for quality and bid £13.6 million to carry out the works.

Related documents:

The Bridge:

Facts & Figures

Opened 1964, 2.5 km long, Main span 1006 metres
divider
  • No restrictions on bridge (19:34 UTC 04/02/12)